Bulk Earthworks: 99 Hogarth Drive
|
|
|
Located within the Harris Crossing master-planned community, the project involved bulk earthworks for the approved over 50s life-style living resort, import of general fill (CBR 3 -200mm screened) 156,162t.
Works include tree clearing and grubbing, stripping of topsoil, earthworks (cut to fill), batters to future stages, excavate, remove and replace unsuitable material, erosion and sediment control, dust protection, spreading topsoil, hydromulching, and testing.
Works include tree clearing and grubbing, stripping of topsoil, earthworks (cut to fill), batters to future stages, excavate, remove and replace unsuitable material, erosion and sediment control, dust protection, spreading topsoil, hydromulching, and testing.