Echlin Street Reservoir
|
|
Excavation and removal of 330,000 tonnes of rock from the former West End Quarry site to create a foundation for two new steel water storage tanks of combined capacity of over 70ML.
Rock was drilled and blasted in strategically planned sequencing of 12 blasts.
Management of 180 B-Double movements per day.
Rock was drilled and blasted in strategically planned sequencing of 12 blasts.
Management of 180 B-Double movements per day.