A new concrete carpark was constructed for the popular Twin City Hotel establishment.
Works consisted of stripping topsoil 75mm.
Supply and place 100mm thick subtype 2.3 gravel subbase.
Supply and install 2 900x900mm grated inlet pits and connect to existing Council infrastructure.
Lay 150mm concrete pavement N32 and final linemarking.
Works consisted of stripping topsoil 75mm.
Supply and place 100mm thick subtype 2.3 gravel subbase.
Supply and install 2 900x900mm grated inlet pits and connect to existing Council infrastructure.